Task 6 Oct 2020 Final Exam Solution Nebosh OBE
Task 6: Permit-to-work system
Question 6: The organization has an
effective permit-to-work (PTW) system.
Why should a PTW be used to help manage this
storage tank modification?
(Marks-10)
Note: You should support your answer, where
applicable, using relevant information from the scenario.
Method of Answering:
1-Introduction: what is PTW system?
2-Body of the answer: why it is necessary for tank modification specifying
the importance of PTW
3-Conclusion
ANSWER:
A TECHNICAL MEASURE
DOCUMENTED CONTROL PROCESS THAT TAKES ACCOUNT OF ALL PREDICTED
INTERACTION BETWEEN THE WORKERS, THE ENVIRONMENT, AND THE ASSOCIATED HAZARD CAN
BE TERMED AS PERMIT TO WORK. IT DEFINES THE SEQUENCE OF WORK DETERMINING
THE PROCEDURE AND PRECAUTION TO CONTROL HAZARD AND MAJOR ACCIDENT.
THE PROPOSED TANK
MODIFICATION IS NON ROUTINE WHICH HAS TO BE CARRIED OUT WITHOUT THE
SHUT DOWN OF PROCESS AND A COMPETENT CONTRACTOR IS ASSIGNED TO PERFORM
THIS TASK. THIS MODIFICATION SHALL BE CARRIED WITHOUT ANY INCIDENT AND SAFELY.
THE RISK INVOLVED IN THE
PROPOSED TECHNOLOGY OF TANK MODIFICATION IS VERY HIGH DUE TO THE
PRESENCE OF TOXIC CHEMICAL SUBSTANCE THE RELEASE OF WHICH WILL BE DISASTER TO THE
WORKERS NEAR BY RESIDENTS, SCHOOLS AND BUSINESSES.
THIS TECHNOLOGY IS SAFE
AND USED WORLDWIDE IF DONE WITH PROPER CARE AND IMPLEMENTING
THE EXISTING AND ADDITIONAL CONTROL MEASURES SUCH AS SSOW, PTW, SUITABLE
INDUCTION TRAINING AND SUPPLEMENTARY EMERGENCY ARRANGEMENTS.
THE MOST CHALLENGING
TASK IS TO MANAGING CONTRACTOR
AT SITE ESPECIALLY IN THIS CASE WHERE THE RISK MITIGATION CAN BE DONE ONLY THROUGH
IMPOSING PTW SYSTEM.
THE PTW SYSTEM WILL
INCLUDE THE EXPLANATION
OF ASSOCIATED RISK ASSESSMENT, CHANGES MADE IN PLANT FOR THE SAFETY PURPOSE, AND
ENLISTED ALL NECESSARY PRECAUTION ON PTW FOR THE DESIRED NON ROUTINE TANK
MODIFICATION.
PTW SYSTEM WILL ALSO
INVOLVE A PHYSICAL CHECK ON THE CONTRACTOR IN TERMS OF AWARENESS
OF ASSOCIATED RISK, WORK METHODOLOGY, THEIR COMPETENCY AND APPROPRIATE
USE OF SPECIFIED PPE. PTW ALSO EXPLAINS TO BE ENFORCED ALONG WITH OTHER SITE
ACTIVITIES BY THE METHOD OF ACTIVE MONITORING IN ORDER TO THE ENSURE THE WORK
PROGRESS WITH COMPLETE SAFETY. THE CONTINUOUS SITE SUPERVISION AND MONITORING
WILL ALSO HELP ON CHECKING THE EFFECTIVENESS OF PTW SYSTEM AND RESOLUTION
ON THE QUERIES WILL ALSO BE PROVIDED BY THE PROCESS OPERATOR AND INDEPENDENT
SITE CONTACT.
THEREFORE THE
IMPLEMENTATION OF PTW SYSTEM FOR THE TANK MODIFICATION TASK IS IMPORTANT
AND IMPOSED
IN ORDER TO CARRY OUT HIGH RISK ASSOCIATED WORK SAFELY.